156B Week 10
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Built device
Parameters such as drying times still need to be calculated
Issues with vibrations in the linear guide that need to be addressed
Accomplishments from Previous Week
PCB created and wired- works well- Cindy
Enclosure created for device - Cindy
Enclosure for electronics completed - Marco
Developing Code for entire system - Marco
Smearing Mechanism completed and added to entire enclosure- Kevin
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Rearrange device to not incorporate Hematek
Finish GUI
Minimize user inputs
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Do not mention the Hematek or integrate device to it
No user inputs should be required
Risks and Areas of Concern
Stepper motor is having many issues and vibrations in the smears may be inevitable
Schedule
Report and Website due Friday June 7th