*156B Finals Week
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Completed Device
Accomplishments from Previous Week
Assembled the device to not incorporate any aspect of the Hematek
GUI created and implemented to code
Stepper motor was reconfigured to minimize vibrations in the system
Smears were made and imaged
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Schedule
Final presentation will be Wednesday to present our final device and poster
Budget (list amount spent and amount remaining)
Running Total
$1,887.09
Budget
$2,000.00
Budget Left
$112.91
Progress on Report and Webpage
Both completed