156B Week 1
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
The initial designs of the nerve lengthening system are forming
Accomplishments from Previous Week
Meet with instructor
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Brainstorm and create our initial design
Discuss our design plan with sponsor
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
The sponsor schedule a new meeting time with us and want us to send him an update of our internal discussions
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Look at previous team's work (03/28/2019 during Risk Reduction presentation)
Pay attention to the time (04/02/2019 during the first lecture)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Time is an important factor that can limit us to test new designs like the lead screw system.
Assemble battery, microcontroller, and stepper motor in a small case.
Resources or Information Required but not Available
None
Schedule
Describe the upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$0.00 spent
$1500.00 remaining
Progress on Report and Webpage
Internal pages up until the current week are complete
The front page is completed
The team website has been organized