Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Completed
Accomplishments from Previous Week
Completed/presented the project;
Finished up reports, posters;
Goals for Next Week (list names after each item). Use specific and measurable objectives.
N/A
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor is happy with the final product delivered and says he might ask us for help in the future steps;
Sponsor says he will pursue patent and might add our names;
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor commented on our poster and report. Both are being edited to incorporate Professor's insights;
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Progress on Report and Webpage