Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Assembled fittings for pump
Designed mixer
Accomplishments from Previous Week
Finished design of mixer, confirmed with Tom and Ian regarding fabrication
Drawings: Mixer.pdf
Tubing and fittings arrived
Fittings for the pump assembled
MOSFET for valve control soldered
Sump sealing test in progress
Pressure Relief Valve purchasedÂ
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Start machining sump (Zixuan Lan)
Assemble heater with overtemp switch and solid state relay (May Lu)
Finish sump sealing test (Yuting Huang, Yanjun Pan)
Drill and tap 6 1/4'' NPT on sump (Yuting Huang, Yanjun Pan)
Purchase 304 Stainless Steel Block for mixer (Yuting Huang)
Assemble system (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor will prvide epoxy for RTD mounting (1-23, in person)
Sponsor provided two heaters with different electrical power (1-23)
Sponsor will provide pressure regulator for LN2, and we will purchase pressure relief valve for LN2 (1-23)
Wiring diagram for pump revieved (1-24 email)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Wrap RTD with Gasket tape after epoxy applied (1-24 in person)
Consider using vacuum jacket pipe for LN2 (1-24, in person)
Asked sponsor if they have any available
Perform leak testing on sump (1-24, in person)
In progress of testing
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None recieved
Risks and Areas of Concern
None
Resources or Information Required but not Available
Cryogenic lab safety approval
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
amount spent : 625.3
amount remaining: 2408.43
Progress on Report and Webpage
impact on society finished