Overview of Status of Analysis, Design, Fabrication, Tests, etc.
System diagram updated (most likely finalized)
Prepare for drilling and tapping the sump for fitting installations
Accomplishments from Previous Week
Purchased Temp Sensors and RTD extension wires
Decided to purchase LN2 from UCSD market place:
200L at 35psi (2.4 bar): $76.71 + shipping + bottle rental +etc
Based on quote from AIRGAS for non-UCSD price: Delivery $43, Fuel Surcharge $9.2, Airgas Hazard Charge $26.8, Bottle rental fee $4.31/day (should be lower from UCSD marketplace)
Estimate total of less than $200 (GOOD)
Sponsor confirmed to provide heater
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Purchase tubing, fitting, insulation before Tuesday (Get Heater inlet / outlet size from sponsor on Monday, hopefully) (Yuting Huang)
Design small mixing box to mix 6 channels into 1
Drill & tap sump for fitting installation before Friday
Start system assembly
Complete safety training for LN2
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sump crafted by Tom (11.5 L) suitable for project (1-19, phone)
Suggested all copper tubing (1-19, phone)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Suggested external mounting of RTD on a flattened side of copper tubing (1-18, in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
RTD mounting
Could not find suitable heat conductive epoxy that can withstand the low temp;
Current idea: use gasket tape to secure RTD to tubing
Need cryogenic thermal paste between sensor and tubing?
Resources or Information Required but not Available
Heater inlet / outlet sizes (will probably hear from sponsor on Monday)
How to purchase through UCSD marketplace (require UCSD business account)
Get approval for LN2 in lab (Ian is working on it)
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent last week: $166.27
Total spent: $166.27
Remaining: $3033.73
Progress on Report and Webpage
Report on schedule
Project description completed, individual component analysis attached