Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Run Low Speed Test and collect data by end of week
Accomplishments from Previous Week
Assembled and mounted remote fill
Wired wiring harness
Wired and tested fuel pump (it works)
Finalized waterloop
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Fire Engine and low speed test (Everyone)
Finish wiring electrical box (Everyone)
Adjust Throttle Cable (Bicky)
Machine Parts for Dampers (Dan)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Out of Town
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Resonance problem
Get data for low speed
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Machining Torsional Coupler
Not enough time to machine torsional coupler
Electrical/Controls Debug
Fuel rail leaks, couldn't start engine.
Resources or Information Required but not Available
EE major
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Progress on Report and Webpage
Finished 2nd draft of report and webpage