Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Run Low Speed Test by end of week
Accomplishments from Previous Week
Coolant System Connected
Fuel Fill Plate Manufactured
Mounted Throttle System
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Complete Remote Fill System (Alec)
Fire Engine and low speed test (Everyone)
Finish wiring electrical box (Ben/Alex)
Adjust Throttle Cable (Bicky)
Machine Parts for Dampers (Dan)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Out of Town
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Resonance problem
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Machining Torsional Coupler
Electrical/Controls
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Progress on Report and Webpage