Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Control station platform will need to be modified to be able to accommodate the electrical box.
The control interface box needs to be reworked and then manufactured (placement of interface controls can come later).
Accomplishments from Previous Week
The 4 thermistors and RPM sensor have been wired into the electrical box
An adapter was manufactured to attach the servo to the water valve
The water valve was modified to be able to couple the servo to it.
Engine quick disconnect panel attached
Coolant overflow system routed
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Assemble:
Complete Driveline Assembly (Ben)
Sensors + Electronics Package (Ben)
Finish Engine (Alec/Bicky)
Throttle system onto dyno (Bicky)
12v system (Daniel)
Finish Wiring Electrical Box (Ben)
Attach Fender Fill Plate to Frame and connect to fuel tank (Alec)
Design
Calibration Mass
Water Brake Inlet Valve Control Package (Alex)
(Adjust the) LabVIEW program for the final control package (Alex)
Control Station (Alex)
Manufacture
Flywheel (Daniel)
Engine Coupler (Daniel)
Inlet Water Control Element Housing (Alex)
Control Station (Alex)
Remote Fill Flange on Fuel Tank(Alec/ Alex welding)
Purchase
Extension Cord/Cable Reel (Ben)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent $115.62
Remaining $601.04
Progress on Report and Webpage
Finished first draft on report
Draft of website uploaded