Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Minimum design finished
Bulb mount redesign in proggres
Lifting mechanism assembly in progress
Linear slider for bulb assembly in progress
Prototype design 2 assembly in progress
Accomplishments from Previous Week
Begun wiring for simulated finger tests
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Final assembly of box (Naif and Inri)
Finish simulated finger testing and results (Thomas and Jason)
Poster (all)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Preliminary Design Review presentation May 23
Want to see the procedure for the simulated finger test
Will be delivered once testing us fully underway, need more discussions with Steve Roberts
Leaving the controller for power management until Week 10, worried about time
Shared concern, moving testing along as fast as possible
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Time
Finishing up loose ends
Resources or Information Required but not Available
Simulated finger test in progress
Schedule
Simulated finger testing
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent: $560.12
Remaining: $3,939.88
Progress on Report and Webpage
Webpage and report updated accordingly