Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finalizing data taking, processing data taken the past few weeks
Resuming assembly and refitting of test bed to revised height
Draft poster completed, proceeding to revision phase
Revising report, website
Accomplishments from Previous Week
Water sealing complete, polycarbonate and vinyl materials acquired
Test bed will no longer be fully housed in polycarbonate, only top
Data gathering with corresponding accelerometer, pressure, and mass flow data via Raspberry Pi
Testing performed with accelerometer connected directly to the pipe. 10% reduction in noise.
Draft poster completed and submitted
Peer reviews on website and project report received
Data taken from accelerometer while adhered directly to piping
Speed of sound through FR-4 grade PCB composite computed
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Revise website as per peer report ALL
Revise project paper as per peer report ALL
Process data and search for trends and patterns according to previously stated statistical techniques ALL
Calculate speed of sound through silicone adhesive Gordon
Finalize test bed: Attach proper supports and put together (Varnished wood, aluminum housing, vinyl walls and polycarbonate top) ALL
Pick up 80/20 brackets and bolt assemblies from distributor. Sam
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Lowered the sampling rate of the pressure sensor from 500 Hz to 100 Hz due discrepancy in number of points processed to what was expected.
Drained out water in pipes to see correlation in the second transient. Still processing data.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Try bonding accelerometer to pipe directly
Bonded it with thin layer of silicone rubber
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Reword several sections of website and report
Write less "clunky"
Add budget data onto website
Schedule
Update Gantt chart
Finalize test bed 6/8/17
Budget (list amount spent and amount remaining)
Amount spent: $808.85
Amount remaining: $1691.25
Pending cost of polycarbonate sheet and vinyl
Added cost for additional aluminum attachments
Hex nuts and bolts
Progress on Report and Webpage
Report and webpage are going to be finalized this Friday.
Inclusion of final results
Final conclusions and future recomendations