Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finish the risk reduction for image processing by using fish eggs
Finish Analysis for entrance length effect for fully developed laminar flow
Wall material
Chamber diameter
Chamber length
Have one possible pump selection
Accomplishments from Previous Week
Start risk reduction
Finish risk reduction power point
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Set up the communication between actuator (pump), micro controller, and camera
Have the prototype chamber design
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Good presentation on risk reduction. However, few questions are mentioned as well
Fiducial
Trigger camera to take images at constant time to figure out the location change rather than using fiducial
use two bands to keep object always between two bends
Tube
Figure out the diameter of the tube
Need diffuser to enable laminar flow
Chamber
How to connect pump to the chamber
What material will be used
Bubble
How to release bubble in the chamber
Image processing
Need filter to get rid of noise
Take several to find average
Account for depth change
PID controller
Use PID controller for speed control
Temperature control
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
3000
Progress on Report and Webpage
In progress