Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Initial Proof of Concept component analyses done
Buoy Dynamics
Electronics Circuit
Pressure Housing
Further analysis to be done
The electronics housing unit needs to be designed
The electronics circuit design needs to be reviewed and evaluated
The buoy dynamics model was established; the simulation needs to be finished
Accomplishments from Previous Week
Unspooling test was done (Mike and Katherine)
Pressure housing waterproof test was performed (Alvin and Matthew)
Power analysis was performed (Mike)
Buoy dynamics model was established (Katherine)
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Proof of Concept Presentation (All)
Finish Buoy Dynamics Analysis (Mike and Katherine)
Design preliminary circuit schematic and review with Steve Roberts (Mike and Katherine)
Finish waterproofing the housing following initial trial (Alvin and Matthew)
Setup biofouling test (Alvin and Matthew)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Make sure power comsumption analysis is performed; make sure buoy dynamics are modeled (20-Apr-2015 in meeting)
Ensure that the rod which is installed into the seal gland has the proper surface finish; ask Tom Chalfant (20-Apr-2015 in meeting)
The rope should be spooled in an orderly manner and should be taut during the passive period (20-Apr-2015 in meeting)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
The waterproofing test showed concern in the installation of a rod in the Ikelite seal gland
The drawn current of the motor at stall torque may exceed that which the motor driver is rated for
The overall cost of material components could be higher than anticipated
Resources or Information Required but not Available
N/A
Schedule
(27-Apr-2015) Proof of Concept Presentation
Budget (list amount spent and amount remaining)
$522.28 spent
$477.72 remaining
Progress on Report and Webpage
(27-Apr-2015) Webpage updated