Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Final deliverable unit in the process of production
Still needs to be tested
Parts need to be manufactured
Final deliverable PCB in process of assembly
Still needs to be tested to verify power requirements and functionality
Final test needs to be coordinated with sponsor
Final unit must be prepared for test
Final report in progress
Final website design in progress
Final poster in progress
Accomplishments from Previous Week
Thread sealant tested on pressure vessel
Teflon tape re-tested on pressure vessel
PCB board was received
Assembly of PCB was started
GUI design started
Assembly has begun but is incomplete pending the arrival of final SMD components
Poster draft submitted
Goals for Next Week (list names after each item). Use specific and measurable objectives.
PCB board to be assembled and tested before final testing with sponsor (Mike and Katherine)
A separate 3.3V electronics assembly to be created in the case that the PCB fails
Graphical User Interface (GUI) to be completed (Katherine)
Requires user tests and user manual
Final deliverable housing unit to be created (Alvin and Matthew)
O-Ring coupler to be tested
Final test to be conducted with Sponsor (All)
If time allows, an earlier test will be conducted separately in preparation for sponsor meeting
Final presentation for sponsor (All)
Final Report (All)
Final Poster (All)
Final Website (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
No meeting last week
Awaiting feedback to determine when to conduct final test
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Consider using an O-Ring coupler part to avoid the issues with sealant/teflon tape
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
The PCB may not work or fail even after all the components are included
The pressure vessel may not be able to withstand the required pressure rating
Resources or Information Required but not Available
N/A
Schedule
Group meeting 1-June-2015 at 11:00AM
Meeting with Instructor 1-June-2015 at 3:00PM
Meeting with sponsor for final test/presentation TBD
Budget (list amount spent and amount remaining)
$1500 budget
$1316.59 spent
$183.41 remaining
Progress on Report and Webpage
Final Report in progress
To be completed ASAP
Final Webpage in progress
To be completed ASAP