Team 10 Members: Shom Bhandari
Brian Mckenna
Nobuto Ishii
Tomo Yamada Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Heat transfer analysis performed for water interface:
Generic Control Algorithm developed based on DUT feedback to a controller:
· Controller K will utilize feedback signals from the RTD sensor and possibly TU sensors. Heater power may be adjusted by the controller.
·
Accomplishments from Previous Week
Analyzed heat transfer through DUT, thermal interface material, and TU.
Performed preliminary experiment to simulate evaporation of water layer.
Identified functional requirements and constraints.
Considered high risk areas of project.
Overheating of DUT.
Overflow of water off of the DUT.
Plumbing system fatigue and corrosion.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Set up a regular schedule with our sponsor. [Tomo]
Format the website. [Nobuto]
Acquire Labview software (or similar product). [Brian, Shom]
1st meeting with sponsor [Tomo, Nobuto, Shom, Brian]
Generate list of questions, comments, concerns. [Shom]
Purchase materials based on sponsor feedback. [Tomo, Shom]
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Effect of distilled water/ tap water
may possibly cause clogging in the pipe or valve
Consider the duration/life cycle of the material
long tern repetition performance
Create area of expertise in your team
Consider using TU sensors
Risks and Areas of Concern
Detection amount of water on and around DUT.
Only one RTD sensor available for commercial applications.
Applicability of DAQ with system.
Confirmation with sponsor best DAQ to use.
Whether heater on the TU will be utilized in our control system.
Resources or Information Required but not Available
Specifics on TU on the control systems
Schedule
Milestones
week 2
Purchase /acquire equipment
Begin writing control system
Complete the title page for the website
Updated Gantt Chart
.
Budget (list amount spent and amount remaining)
$ 0 spent on equipment
$1500 remaining
Progress on Report and Webpage
Progress on Webpage
Post Internal files
Main page/weekly report page
Uploaded risk reduction slides