Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Fabrication is 95% complete
Critical machining done
75% complete with fastening
Bladders installed and test fit, need to test in bore
Accomplishments from Previous Week
Fabrication as noted above
Testing scheduled for morning of 6/1
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Determine ideal location for air bladders and bond to base (calvin and kristen)
Continue to verify performance mathematically and with simulation (alex and femi)
Finalize fabrication and hand over completed model to sponsor
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Consider alternate methods for mounting optical fiber
Order ceramic ferrules or determine best supplier for sponsors future use
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Discuss all aspects of project with all involved in absence of sponsor
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None
Risks and Areas of Concern
Success of bladders
Epoxy and insulation of fiber optics
Location of bladders, pressure to be inflated to
Resources or Information Required but not Available
None
Schedule
Finalize temporary fabrication for testing on 6/1
Complete final product ASAP after testing
Budget (list amount spent and amount remaining)
Spending thus far about $400.00
No further planned purchase
Progress on Report and Webpage
No change to website
Added more figures to report, elaboration on material, completed peer review
Continued mathematical justification for bladder isolation