2/2012 Bond Projects Progress

Post date: Feb 9, 2013 12:29:37 AM

From Bartlesville Radio News:

The Bartlesville Board of Education held a short special meeting today at the Education Service Center. The majority of the meeting was spent discussing and then approving several bids for the ongoing work at Richard Kane Elementary School. Randy Weatherly of Ambler Architects said most of the project has been awarded with the exception of sod and fencing and that will be done later in the year. Weatherly did recommend rejecting the bid that dealt with the epoxy coating for the bathroom floors and walls because bidders did not bid on the entire package.

The poles and lights at Custer Stadium are being removed prior to the installation of four new poles and their accompanying lights. The new lighting system is scheduled to be operational before the first soccer game of the spring. The current lights and poles were part of a package approved by the Board as surplus items.