Check back here for the latest in major Campus Maintenance updates:
11/12/24 - Deferred Maintenance Related
IN PROGRESS
Cole Complex: Roof In Progress - Expected Completion 11/15/24. Please note ADA access path for entry into building has changed for safety.
Student Union: Roof In Progress - on target for end of November completion.
Davis Fine Arts: Roof In Progress - on target for end of November completion.
UPCOMING
Cole Complex: Classroom Carpet 210- Expected completion 3rd week of December
Jones Hall: Roof to begin in the next 2 weeks
Sullivan Hall: Roof to begin in the next 2 weeks
*WORK WILL COME TO A STOP DURING THANKSGIVING WEEK.
11/12/24 - Non-Deferred Maintenance Related
UPCOMING
Cole Complex: Theater Lobby Carpet scheduled for 11/15/24.
Cole Complex: ADA sidewalks are being reviewed for better access.
Faculty Home H: House Removal
Faculty Circle: Tree Removal (2 trees)
Ferrell Hall: Main Lobby Hallway Carpet Installation
Ferrell Hall: Admissions Area Carpet Installation