Below is our original timeline and our actual achieved timeline. Our original plan was drafted in week 3 and had everything prototyped by the end of week 4 and the reset of the term was for debugging. We ended up actually spending weeks 3 through 6 getting prototypes of each system and weeks 7 through 9 completing assembly and doing testing. One reason for this is because we would prototype and complete a system such as the frame before moving on to a different system such as the wheels.
Plan:
Executed: