The problems we faced consisted of:
Two groups members had covid
Members in class did the designing and building
Virtual members did the website and research paper.
Combined groups with group 7 so we can decrease the work load
We repeatedly lost files due to some issues saving them
Moved the files to the main desktop, so it was saved there
ModelSmart3D bridge did not carry a lot of load
Added more supports in the truss to better distribute the forces.
What we could have done differently:
Manage time better
Cut materials longer in length than what we thought we needed
Made sure we used materials sparingly until we were certain that we had enough materials
Bargain better
Things that failed :(
Although we had a very successful bridge, our simulation was a bit of a failure
One time a file got corrupted and said it had 0 bytes.