BASF, USEPA, EGLE, Municipalities, and Legislative Officials claim to be "Working Together" to solve BASFs Toxic and Hazardous Venting Groundwater to the Great Lakes in Wyandotte, MI (3000 gallons per hour).
See for yourself how this has been going.
Below, Congresswoman Dingell calls for Swift Action - July 08, 2022
BASFs 30 Percent Design Timeline Submitted to USEPA on Sept 5, 2022- Starting Construction October 7, 2024. Two years after Dingells call for Swift Action.
Below USEPA Construction Timeline Slide from Aug 23, 2023 gives BASF until at least Feb 2027 to maybe begin construction. This is nearly 5 years after Dingells 2022 call for SWIFT Action, and a bonus 2.5 yrs on top of when BASF said they would start Construction
This is incredulous when you realize EGLE has a Court Order from 1985 (that they ignore to enforce) that contains the exact same required ground water "inward gradient" from BASF right now, that BASF proposes to meet sometime beyond 2027 when they may begin construction.
According to USEPA's slide of Aug 8 2023, BASF's release of Toxic and Hazardous groundwater contamination
(at 3000 gallons per hour) is being allowed continue into infinity and beyond
How is this acceptable to our Elected Representatives, allowing such contamination to the Public Resources of the communities they are supposedly protecting?
BASFs March 04 2024 60 PCT Submittal to USEPA and EGLE
pushes the Remedial Start Up date out beyond 2030...
6 more YEARS of Toxic Hazardous Waste Releases to the Great Lakes at Wyandotte is what the 2024 BASF 60% design provides.
BASF has NEVER kept to any schedule they have promised the State nor the Federal Agency's to remediate Northworks
1980 State Consent Order - State Court
1985 State Consent Decree - Federal Court
1994 USEPA Adminstrative Order on Consent
2000 BASF Letter to USEPA on Corrective Measures Implementation at NorthWorks
2009 USEPA RCRA Letter on Imminent and Substantial Endangerment - 2010 required Remedation of Sediments
2018 USEPA RCRA Letter for 90days to Finalize NorthWorks GroundWater Remediation Actions
The ONLY remedial construction BASF ever implemented was their design and startup under the 1985 State Consent Decree,
which they shut off in 2019 without permission from the State nor the Court, a statutory requirement under the 1985 Consent Decree.
Currenty, BASF is using the Detroit River-Trenton Channel as its own personal dumping grounds, releasing Toxic Hazardous WASTE into the Critical Assessment Zone (CAZ) of the Wyandotte Municipal Intake at 3400 gallons per hour (EGLE Calculation). This is a Felony violation that the State, USEPA, Congresswoman Dingell, and BASF are fully aware of is occurring.
The State and USEPA have no monitoring plan in place to protect the Public Resource of the Detroit River.
Analysis:
Dingells "SWIFT" call for action in July 8, 2022 means + more years of Toxic and Hazardous Waste releases above Water Quality Criteria to YOUR Great Lakes based on USEPA's timeline slide presented to the public on Aug 8, 2023.
While Dingell called for SWIFT Action on July 8, 2022, and BASF sent USEPA a Construction Start Date of Oct 07, 2024,
USEPA Responded to the Public on August 23, 2023 giving BASF till Feb 2027 to maybe START hydraulic remedial construction at North Works.
While BASFs own 30 Percent Design submittal of Sept 05, 2022 had a Construction Start Date of Oct 7, 2024 and the Completion and Full Operation / Demobilization of the Hydraulic Barrier by Feb 26. 2027, USEPA extended BASFs construction start date, gratis, til Feb of 2027 or beyond, when ever BASF feels like it.
BASFs 60 PCT Design of March 04, 2024 now has a Startup of a Remediation system in 2029-2030 !!!
USEPAs latest Timeline for Construction BEGINNING,
is now AFTER the date when BASF themselves
submitted they would be Completely Finished!
How does this Happen?
Nevermind that BASF is in Exceedance and Violation of Michigan Water Quality Criteria and Court Order NOW
and allowed to continue for the next 6+ Years.
Why is EGLE completely silent when it has an enforceable Court Order in hand since 1985 for BASF North Works to maintain
an inward gradient with an existing Treatment and Extraction System (as designed, built, and already installed by BASF in 1986) ???
As of today, right now, there remains no Federal or State or Legislative
accountability, no monitoring, no compliance, and no ENFORCEMENT
to halt Toxic and Hazardous venting groundwater from being released
by BASF North Works!
Your Environmental Oversight Tax Dollars at work,
helping a polluter keep polluting til 2029 and beyond.
Thanks USEPA and EGLE Staff and Management for your
SWIFT ACTION at BASF North Works.
BASF couldn't continue to pollute the Great Lakes without your full cooperation in extending construction timelines, pushing back startup dates,
and ignoring existing Court Orders to
"Halt the Flow of Contaminated Groundwater to the Detroit River"
(1985 State Consent Decree)