Fall 2021 Milestones:
Milestones and Deliverables Time Sheet: (September 10,2021)
A list of milestones and deliverables as well as team member responsibilities
Research on Elizabethtown: (September 24,2021)
Description of watershed, current BMPs in place, and contains contour data for the watershed
Current BMPs in Buffalo Lake Watershed: (October 8, 2021)
Design plans for the current BMPs in the Buffalo Lake watershed
Precipitation and Watershed Delineation: (October 15, 2021)
A watershed delineation for the Buffalo Lake watershed that shows how runoff flows as well as precipitation data
Soil Mapping: (November 5, 2021)
Soil map of expected area used for BMP design
AutoCAD Sand Basin Design: (November 12, 2021)
Preliminary design drawing of Sand Basin
Potential BMP Effectiveness: (November 19, 2021)
Analysis of standards and topography from North Carolina and Tennessee BMP projects
Outlines questions obtained during poster presentation and goals for spring semester