Date: 02/08/2021
6:46 AM -
Workers are seen mobilizing on the west wing roof of the Academic classroom and laboratory complex building (ACLC).
6:54 AM -
Workers can be seen working on the ceiling truss structure on the west wing roof of the ACLC.
7:06 AM -
While workers are working on the truss system on the west wing, site engineers on the right wing are seen inspecting the formwork/falsework that was laid out the previous week;
9:51 AM - An individual worker is installing window panes on the south side wall of the ACLC west wing.
11:25 AM - A crane is used to transport concrete to the east wing of the ACLC. Workers can be seen filling the column formwork (completed last week) with concrete.