Work Breakdown Structure (WBS)
Updated 4/5/2025
Updated 4/5/2025
1.1. Project Charter
1.2. Preliminary Scope Statement
1.3. Kick-Off Meeting
2.1. Team Contract (PR1)
2.2. WBS (PR1)
2.3. Draft Schedule (PR1)
2.4. MBTI Team Analysis (PR1)
2.5. Updated Scope Statement (PR2)
2.6. Gantt Chart (PR2)
2.7. Probability/Impact Matrix (PR2)
3.1. Communications
3.1.1. Meeting Minutes
3.1.2. Sponsor Feedback
3.1.3. Google site
3.2. Accessible PPT Template
3.2.1. Team Accessibility Training
3.2.2. Accessibility Training Completed (Milestone 1)
3.2.3. CCB/UMassD Brand Identification Review
3.2.4. Deliverable 1 Slide Deck
3.2.5. Deliverable 1 Accessibility Pre-Screening
3.2.6. Deliverable 1 Accessibility Specialist Vetting
3.2.7. Deliverable 1 Completed (Milestone 2)
3.3. Accessibility Resources
3.3.1. Resources Research and Identification
3.3.2. Resource Word Document Creation
3.3.3. Deliverable 2 Accessibility Specialist Vetting
3.3.4. Deliverable 2 Completed (Milestone 3)
3.4. Recorded Accessibility Presentation
3.4.1. Deliverable 3 Slide Deck
3.4.2. Deliverable 3 Transcript & Recording
3.4.3. Deliverable 3 Accessibility Pre-Screening
3.4.4. Deliverable 3 Accessibility Specialist Vetting
3.4.5. Deliverable 3 Completed (Milestone 4)
4.1. Weekly Project Updates
4.2. Progress Report #1
4.2.1. Prepare and Practice Presentation (PR1)
4.2.2. Post Information Online (PR1)
4.3. Progress Report #2 Documents
4.3.1. Assemble All Documents (PR2)
4.3.2. Prepare and Practice Presentation (PR2)
4.3.3. Post Information Online (PR2)
5.1. Final Presentation
5.2. Project Notebook