Mailbox Committee: Mark White, Naomi Tulenchik, Cindy Lemm, Michelle Hunt, Joyce Thuening
*Cluster Mailbox inquiry to look into cost, location, permission from Post Master, future expansion
Dock Electricity (Dave Pierre, Todd Anderson, Scott Tulenchik, and Joyce Thuening.)
–Will be done in phases based on allowable budget
2024 Phase: I was completed and electricity was added to the south leg.
2025 Proposed Phase: TBD but the tenative plan is to update portions of the East Leg electrical.
2026 Proposed Phase: Continue to update/finish the East Leg electrical
2027 Proposed Phase: Update/finish the West Leg electrical
Road Project (Committee: Joyce Thuening, Dave Pierre, Justin Payment, Scott Tulenchik)
2025 suggested plan:
Apply gravel on the on the bog 10-12 loads to continue a 4" base on the road. Apply 18-20 loads of gravel on Isle Harbor roads, this is still working on the 2" base. We would apply gravel to areas (to be decided) that have not received gravel.
2026 suggested plan:
Apply gravel on the on the bog 10-12 loads to continue a 4" base on the road. Apply 18-20 loads of gravel on Isle Harbor roads, this is still working on the 2" base. We would apply gravel to areas that have not received gravel, this will finish the 2" of gravel within Isle Harbor and we will be able to start on the 4" base.
If we would continue with the above plan, we would complete the 4" base all roads in 2029. According to the contractors that we are working with many of Isle Harbor roads do not need the 4" base, so the main roads in Isle Harbor would be completed sooner. Based on the agreement with Federal Dam for the $5,000 reimbursement and the road usage, we will continue to add gravel to the bog road every year with the 10-12 loads per year would add gravel to each section every five years as a maintenance plan. A similar plan for Isle Harbor roads should be put into place with 5-10 loads of gravel each year.
Dock Project -completed 5/2020
The Titan Deck dock panels have been placed and finished the rest of the perpendicular docks. With the completion of the dock project, the Dock Committee has been disbanded by the board. 5/2020
The 2025 Budget includes 5 panels that went missing in the high waters in 2022. As the budget allows start putting in stairs with rail walkways from the ground to the dock system.