Study for Widening Airport Parkway Commences

Post date: Jan 28, 2015 10:25:46 PM

The City held its first public open house on Jan 27, 2015 to present and solicit feedback on its proposal to widen the airport parkway.

This project is proposed to have a 3 stage rollout as follows:

Stage 1: expand Airport parkway to 4 lanes divided hwy between Hunt Club and Brookfield

- Completion is envisioned for 2019, Projected Cost: 31m$

Stage 2: expand Lester Rd to 4 lanes between Albion Rd and the Airport Parkway

- Completion envisioned for 2020-2025 timeframe, Projected Cost: 13m$

Stage 3: expand Airport parkway to 4 lanes divided hwy between the Airport and Hunt Club

- Completion envisioned for 2026-2031 timeframe, projected cost 36m$

End-End project cost = 80m$

The study is expected to go through 3 rounds of public open houses and be finished in the latter half of 2016.

More details...Airport Parkway Widening: Details