Design of 1400 Square Feet addition .
Status Update:
1) Structural Calculations Submitted with Architectural package
2) Additional truss and window buck details in CAD sent to Ron,
3) Ron requested to meet with city plans reviewer to expedite permit. ( 10/7/2009)
10/7/09, Ron wants JBC to meet w/ city officials to answer questions week 10/12/2009, to auth. payment of 2 hrs and pre pay engineer ($300)
Ron to advise!
10/8/2009: Carl works called to set up meeting for Monday next week, but engineer waiting on signed authorization and $300 payment.
10/13/2009: Meeting with Cliff, Carl and city inspector set for 12 PM, to review Architectural comments RE: wind Loads on doors and windows.Met w/ Harry, needs several drawing details such as wall sections showing insulation, furring strips, etc.. needs window and door city form schedule, for all windows and doors, including mullions size and attachment. Needs roof application corrected with correct information, roof sketch, Architect to sign and approve NOA product approval forms . Needs energy calculation forms, for AC, and mechanical. Plumbing: Need to show notes about 3 inch main pipe direction change, and notes regarding septic tank. Also, must get approval from Fred Morgenstern, the Health department for septic tank "existing" before approval by the Building Department. Cliftin Folkes needs all city comments per meeting memorailized in writing and sent to Ron Kacmarsky for action.
10/21/2009: Clifton is trying to meet with Harry at city with Ron and Carls to address several comments pending permit issuance.