This page provides the latest updates on the construction of the new Lincoln Park Elementary School. The school is being built to address growing enrollment, relieve overcrowding, and provide modern, high-quality learning spaces for students. The new neighborhood school is expected to open for the 2027–2028 school year.
Construction at Lincoln Park Elementary continues to make steady progress. Parking lot stabilization has been completed, providing on-site parking for construction crews and reducing the need for parking on nearby public streets. Structural steel, bar joists, and roof decking are now in place, with roofing work well underway. Masonry work continues to advance rapidly, with crews making significant progress on the building's exterior.
Construction continues to move forward at Lincoln Park. Crews are finishing the exterior foundations, and block laying began this week, allowing the structure to start taking shape. The team is also awaiting final resolution on the parking area design and remains optimistic about a positive outcome!
Work at Lincoln Park is advancing well. The soil cement process began on the newly cut roadway, and the building slab is scheduled to be poured, pending confirmation of proper soil bearing capacities.
Progress is underway in the construction of the Lincoln Park Elementary School. Most of the grubbing and clearing, including tree removal, is complete. The site is now fully fenced to ensure safety and security. Next up, a rock construction entrance on West Wyomissing Court is being installed.