Stages of Fabrication
Assembling of support frame
Assembling of open channel
Application of surface finishing
Preparation of water tank
Electrical connection
Assembling of components
Steps involved:
Cutting and welding of steel pipes
Welding of steel plates
Welding of pipe clamps
Welding of wheels
Drilling of holes for bolts
Steps involved:
Cutting of acrylic sheets
Joining of acrylic sheets
This is required so as to prevent formation of rust on support frame.
Steps involved:
Grinding of steel to remove rust
Application of red-oxide
Application of paint
Steps involved:
Cutting of water barrel
Drilling of holes in water barrel for pipes
Joining of open channel to water tank
Steps involved:
Placement of emergency switch and indicator lamp in control box
Electrical connection of pump to emergency switch, indicator lamp and plug
Steps involved:
Use of PVC adhesive to join PVC pipes, pipe fittings and different components
Bolting of pump and control box to support frame
Placement of pipes, valves and other components on support frame
Precautions Observed
Over the course of the project, certain measure were observed so as to ensure its successful completion. These measures include: