PHASE V

Faust Middle School Renovation w/ Alternative #1 Included

o Notice to Proceed Issued ~ March 5, 2021

o Site Mobilization ~ Late March 2021

o Begin Renovations at all areas with the exception of Superintendent’s Office, BOE Office, BA Office, CST Office, ISD Office ~ Late March 2021

o Substantial completion of work ~ September 2021
o Receive Certificate of Occupancy ~ October 2021