PHASE IV

Preliminary/Projected Construction Schedule Items

o February 17, 2021 ~ Bids were received

o March 5, 2021 ~ Notice to proceed for all projects was issued to Dobco Inc. by the Board's attorney, Chasan, Lamparello, Mallon, & Cappuzzo


UPDATED CONSTRUCTION PROGRESS REPORT- August 8, 2022

Faust Middle School Addition

o Notice to Proceed Issued ~ March 5, 2021

o Site Mobilization ~ Late March early April 2021

o Completion of Building Foundations ~ May

2021

o Commence Steel Erection ~ Late May 2021

o Complete Building Erection ~ July 2021

o Complete Building Enclosure ~ January 2022
o Received Temporary Certificate of Occupancy

~June 2022