PHASE IV
Preliminary/Projected Construction Schedule Items
o February 17, 2021 ~ Bids were received
o March 5, 2021 ~ Notice to proceed for all projects was issued to Dobco Inc. by the Board's attorney, Chasan, Lamparello, Mallon, & Cappuzzo
Footing Forms along Column Line E
Electrical Conduits at New Transformer Loation
Right Side of Site Looking at Multi-Purpose Room Area – Uhland on the right
Center Portion of Site – Lookioomng at new Multi-Purpose Room Area
Left Side of Site – Annex Builidng on the left
Doured Footing at Column 15/C.1 and 16/D.0
Footing Along Column Line E
Foundation Wall along Column Line E
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Footing excavation along column line E.0
Footing excavation along column line 15.0
Foundation backfill along column line A.)
Footing along column line C.0
Storm water pipe installation near the Annex
Area drain
Additional protection near the Annex
Addition grease pit wall forms
Addition footing formwork
Addition stockpile at center of site
Sitework near Annex
Addition – Foundations at Gym
Area Storm Drain Structure
Addition – Grease Pit Slab
Damproofing at foundation wall
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Continues on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Preparations for the Construction of the New Faust School Addition
Preparations for the Construction of the New Faust School Addition
Preparations for the Construction of the New Faust School Addition
Preparations for the Construction of the New Faust School Addition
Preparations for the Construction of the New Faust School Addition
Preparations for the Construction of the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Construction Begins on the New Faust School Addition
Water Company Conducting Preliminary Work
Storage Shed Being Relocated
Storage Shed Being Relocated
Storage Shed Being Relocated
Storage Shed Being Relocated
Storage Shed Being Relocated
Storage Shed Being Relocated
Storage Shed Being Relocated
Storage Shed Being Relocated
Temporary Construction Fencing Going Up
Temporary Construction Fencing Going Up
Temporary Construction Fencing Going Up
Temporary Construction Fencing Going Up
Temporary Construction Fencing Going Up
Storage Containers Being Delivered
Faust Middle School Addition Site
Temporary Construction Trailer
o Notice to Proceed Issued ~ March 5, 2021
o Site Mobilization ~ Late March early April 2021
o Completion of Building Foundations ~ May
2021
o Commence Steel Erection ~ Late May 2021
o Complete Building Erection ~ July 2021
o Complete Building Enclosure ~ January 2022
o Received Temporary Certificate of Occupancy
~June 2022