Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Redefining project scope due to COVID-19
Retrieving and distributing supplies from ARMOR Lab
Ordering supplies (adhesives, soldering kit)
Will begin fabrication once supplies are received
Accomplishments from Previous Week
Ordered and received DAQ and transceiver modules
Completed Risk Reduction Presentation
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Meet with Dr. Loh and Morgan (All)
Pick up supplies from ARMOR Lab (Chris)
Distribute supplies to team (Chris)
CAD test stand and circuit encasement (Reuben)
Order soldering kit delivered to (Kaitlynn)
Order adhesive supplies (Reuben)
Fabricate new sensors (Kaitlynn)
Experiment and preliminary testing with Teensy (Chris)
Experiment and preliminary testing with wireless transceiver (Michelle)
Select program to receive, interpret, and analyze data (Michelle)
Finish project design proposal presentation (All)
Work on report (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
PVDF sensors arrived in ARMOR Lab; will work on distribution (3/31 via Zoom)
ARMOR Lab group calendar to minimize lab personnel (3/31 via Zoom)
Maintain open communication with Morgan (3/31 via Zoom)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Department is working on 3D printing access (3/31 via Zoom)
Dr. T will check about getting an oscilloscope for us to borrow (3/31 via Zoom)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Too much text on Risk Reduction presentation slides (3/17 via Google Sheets)
Use more visuals in presentation (3/17 via Google Sheets)
Touch on financials during presentation (3/17 via Google Sheets)
Risks and Areas of Concern
N/A
Resources or Information Required but not Available
Oscilloscope with 4 channels
Schedule
Collect supplies and begin secondary fabrication and DAQ testing
Budget (list amount spent and amount remaining)
Amount spent: $116.59
Amount remaining: $2,783.41
Progress on Report and Webpage
Starting report on 4/2 (select sections due midnight Friday Week 2)
Update webpage with CAD figures and design proposal