May 25, 2020 - May 31, 2020
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
ARC delayed with other projects
looking for new fabrication company
UCSD machine shops did not reply for quotes
Accomplishments from Previous Week
We were able to play with the prototype and discuss changes to be made
trigger hits the handle so we need to make the space bigger between
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Contact outside machine shops for quotes - Rebeca & Anne
Create final files to send for fabricating - Daniel
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
May 26, 2020 (Zoom)
Testing of device strength
envision doing something where you show the pressure needed at the handle
show that it's a really low required input force
Check other patents for data
Reach out to CNC people to see if they have measurement tools
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Time
parts have a high lead time so we may not get them on time
Resources or Information Required but not Available
Schedule
Our focus right now is:
metal 3D printing so we can perform tests
Budget (list amount spent and amount remaining)
$1 spent on 3D print, $5999 remaining
Progress on Report and Webpage
Constantly updating webpage and report