June 1, 2020 - June 7, 2020
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Our final design was chosen and we are waiting for our machined parts to perform official testing
in the meantime we have calculations and possibly force analysis we can do to prove our device works
Accomplishments from Previous Week
Received quotes from 3 different companies
lead times are around 3-4 weeks
Began final presentation
Still working on report
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Sign and submit provisional patent
had a meeting on June 2, 2020 with representation to draft up our patent
will be submitting by June 10, 2020
Final Presentation: June 9th with sponsor
Final Poster Session: June 10th with public
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
June 2, 2020 (Zoom)
wait for more quote replies before we choose which company to proceed with
provisional patent will be filed and we have a year of protection
scheduled our final sponsor presentation for June 9th
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
We won't be receiving our parts on time
we are lucky to be able to continue working on our project because of our patent but as far as the class goes we won't have the final metal parts yet
Resources or Information Required but not Available
Schedule
Our focus right now is:
picking a company to machine our parts
perform tests
Budget (list amount spent and amount remaining)
$1 spent on 3D print, $5999 remaining
Progress on Report and Webpage
Final Draft will be done by June 7th