Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finished verifying software part
Fully assembled the holder using aluminum parts
Finished wiring control panel
Accomplishments from Previous Week
finished testing plc with conveyor and photoelectric sensors
finished assemble one holder and placed order for holder parts to assemble five of them
finished testing plc with peristaltic pump
Goals for Next Week (list names after each item). Use specific and measurable objectives.
finish building injection module (Kaiwen Dou; Bowen Li)
finish assemble injection mount (All)
finish wiring in injection module (Genggeng Zhou; Zhanqing Huang)
finish calibrating conveyor and peristaltic pump (Genggeng Zhou; Zhanqing Huang)
experiment with integrated machine (all)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor got machined holder parts for us, and agreed to manufacture 4 more by the end of the quarter
Sponsor had some suggestions on the mount. we made some improvement on our model
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Nothing specific
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Some students were confused about the PLC parts and simulation. We will do a better job in final report and poster.
Risks and Areas of Concern
NA
Resources or Information Required but not Available
NA
Schedule
by the end of this week finish building injection module and wiring
by the beginning of next week finish assemble injection mount
by the end of next week finish calibration and experiment
Update Gantt chart.
Budget (list amount spent and amount remaining)
3825.33 spent; 6174.67 remaining
Progress on Report and Webpage
finished second draft and added more content