Overview of Status of Analysis, Design, Fabrication, Tests, etc.
We finish the analysis for our risk reduction;
Five different fixture models have been designed .
Accomplishments from Previous Week
Prototyping of our risk reduction components;
Force analysis;
Spring/rubber band selection.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
For winter break, each team member is assigned specific components for research and analysis.
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsors are satisfied with our progress
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor suggests us to do more quantitative analysis and think about potential alternatives.( 12/03/2019 in person)
We finished static force analysis and add potential alternatives in our slides.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Rubber band selection
Resources or Information Required but not Available
N/A.
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
11800 (zero spent)
Progress on Report and Webpage
We uploaded risk reduction slides to our webpage.