Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Analysis:
Finished analysis needed to purchase load cells
Design
Finalized design of all components except the take-up spool key-lock design.
Began design of control system in previous week with Ed Pogue
Fabrication
Fabricated small PP rollers for idler, but need to remachine without bearing holes
Waiting on other PP stock to fabricate take-up spool
Need to begin fabrication of vertical mounts
Tests:
Completed test to determine load cell sizing as discussed in accomplishments from previous week
Will do length tracking test with new higher-torque motor.
Accomplishments from Previous Week
Developed full system CAD as seen in the figure below.
Figure 1: CAD of Entire System except supply spool mount
Setup full system prototype with feeder mechanism, idler pulleys, tension monitoring, servo guide, and horizontally mounted take-up spool.
Figure 2: Full system prototype.
Purchased raw materials, hardware, etc for system prototype and final system.
Contacted CMC about their load cell transducers for tension sensing and received the following quote:
Tension Sensor: 829.99
Amplifier: 629.99
Cable: 89.99
Total: 1549.97
Determined this was out of our budget, and decided to make our own tension system using two 1kg load cells with amplifiers which were determined by the following test.
Setup preliminary tension monitoring system and measured tension in rewind section of the spooling system over 60 seconds
Max tension: 1.2 N
Average tension: 0.42 N
Resolution: 10 mN
Outcome: Using two 1 kg load cells we would have a range of 20 N with a resolution of 5 mN which is sufficient for our requirements.
Figure 3: Tension in rewind section in full system prototype.
Sent purchase order to Roxanne to order load cells and amplifiers.
Jhon and Anthony visited IMS for aluminum stock on the recommendation from the machine shop and purchased aluminum sheets to begin machining vertical mounts.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish full assembly with real parts and raw materials
Idler pulley system (Jhon)
Tension monitoring system (Anthony/Pat)
Feeder mechanism with aluminum side mounts (Iman)
Take-up spool and mount (Anthony/Pat)
Supply spool mount ( Iman)
Servo guide ( Jhon)
Enclosures ( Pat)
Implement control system when higher torque motor arrives for second spool. (Anthony/Patrick by 5/25/19)
Purchase all remaining parts and materials that are required for final fabrication and assembly. (Anthony/Patrick by 5/22/19)
Aluminum stock from IMS
Dry bushings (4x)
PP sheet
PP 5" diameter stock
Begin fabrication of final parts starting on Thursday (5/23/19)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Non-contact material:
Aluminum and other metals should be fine
No rusting
If it is not touching the lumen it should be fine
Aluminum is probably ideal (look into anodize it)
Cleanroom standards
Use dry bearings
Should be fine if enclosed.
Sponsor indicated that our plans to ensure no damage of the tubing was sufficient
Compression test
Compressed air test
Tension test
Sponsor is fine if load cell calibration has to be done every so often as long as we include a protocol
Ordering PP from McMaster is fine
Use PP or anodized steel or aluminum for the base
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Load cells will introduce unknowns into the system and need to account for this (i.e. mounting..)
Need to consolidate slides better and focus on outcome of analysis not the analysis itself.
Discuss cleanroom standards with sponsor including dust and IPX standards
Look back into screw drive system if servo does not work for guide
Get finalized quote from CMC on transducers
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Need to work on better representing our analysis in more consolidated slides
Work on oral delivery better
Better explain the need for this project with our sponsor
Risks and Areas of Concern
Key mechanism for take-up spool cap and shaft mounting
Will discuss with advisor and machine shop staff
Resources or Information Required but not Available
N/A
Schedule
Second report draft and website by this upcoming Friday
PDR scheduled for next Tuesday
Hardware demo to sponsor in two weeks
Final poster presentation in three weeks.
Updated Gannt Chart.
Budget (list amount spent and amount remaining)
Update purchase list
Progress on Report and Webpage
No updates on this yet, will begin working on it tomorrow and the rest of the week.