Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Optics System (in progress)
Create a list of potential lenses which will be appropriate for the lens system (Winnie, Zijun)
Test these lenses on Zemax, interpret results of diagrams (Winnie, Zijun)
Hardware (in progress)
Preliminary designs finished, still need to make adjustments based on lenses. (Andy, Winnie)
Smartphone app (in progress)
App runs on emulator and has simple camera functionalities, but still seeing some issues. (Andy, Mihir)
Accomplishments from Previous Week
Test Hardware
Experimentally determine the required magnification for the Pixel 2 (Zijun)
Research the specifications for the Pixel 2 (Andy, Mihir, Winnie, Zijun)
Housing Design
Analyzing preliminary designs that will maximize ease-of-use and effectiveness (Andy, Winnie)
Smartphone App (Andy, Mihir)
Has basic camera functionalities
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Optics System
Finish lens design, choose and start purchasing lens (Zijun, Winnie)
Hardware
Finish hardware design around the lens design and compile a list of lens housing to purchase (Andy, Winnie)
Smartphone App
Fix the bug with opening the camera function on the smartphone while running the app (Andy, Mihir)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
N/A
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
Intensity of light and allowable intensity to get a clear image
Resources or Information Required but not Available
IEC62471 standard document
Couldn't find the actual document of the standard itself.
Schedule
Upcoming milestones:
Finalized design system and moving on towards purchasing lenses.
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent: $600
Remaining: $900
Progress on Report and Webpage
Reports are up to date .
Webpages updated with reports and presentations.