Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Still need to finalize grip design
Accomplishments from Previous Week
Purchased linear potentiometer and linear actuator
Purchased linear bearings, shaft collars, and rails
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finalize grip design - All
Finalize drawings with Tom - All
Purchase raw materials - Clint
Begin machining - All
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Sponsor liked original grips involving clamping with socket head screws, 4/15 in person - New design drawn up that uses threaded rods and hex nuts
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Shaft collars to lock blocks in place, 4/13 in person - Shaft collars added to replace set screws
LabVIEW integration/control, 4/13 in person - Taiwan lab does not have LabVIEW, investigating other optionsÂ
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
N/A
Risks and Areas of Concern
N/A
Resources or Information Required but not Available
N/A
Schedule
Accomplish the goals for next week
Budget (list amount spent and amount remaining)
$580.22 spent
$919.78 remaining
Progress on Report and Webpage
Background, review of existing solutions, statement of requirements, deliverables, title page, appendix with individual component analysis done.
Applicable standards to be completed by midnight 4/23