Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Finalizing design and components.
Accomplishments from Previous Week
Met with sponsor
Met with Tom & Ian
Met with Steve Roberts
Clamp design
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Purchase motor - Javad
Purchase ball screw - Andrew
Purchase linear potentiometer - Nathan
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Possibly put rubber sheets on gripping surfaces - April 4 over Skype; consulted with Tom and this should be relatively easy
Aim for roughly 50 N of tensile force - April 4 over Skype; confirmed that linear actuators will be able to supply this
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Make progress on report - March 30 in person; Background done, statement of requirements done, individual component analysis done
Be more specific with goals - March 30 in person
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
None so far.
Risks and Areas of Concern
None.
Resources or Information Required but not Available
No concerns at this time.
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
$0 spent
$1500 remaining
Progress on Report and Webpage
Week 2 progress report on webpage
Statement of requirements, individual component analysis, background done for report