Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Prepare for testing
Accomplishments from Previous Week
Jetcat acquired, storage secured, and testing area established.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Order sensing equipment (Microphones, Pressure sensors, Thermocouples)
Fuel and supplies necessary for operation of Turbine
Setup Testing Area, build mount
Successfully start turbine
Contact Professor De Callafon (EBUI 1607)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Ideas are good
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Seek out help from articles and instructors specializing in noise reduction
We have acquired books and articles on noise suppression, see Resources below
Risks and Areas of Concern
Breakout Noise
Cycle Fatigue (Fatigue life)
Mounting Hardware
Resources or Information Required but not Available
Schedule
Get turbine running
Determine noise signature ASAP (Two Weeks)
Budget (list amount spent and amount remaining)
$1500 – Machining
$2400 – Turbine
$3600 Remaining
Progress on Report and Webpage
Upload individual component analysis
Upload progress report and gantt chart