Guidelines for Report
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Testing: In Progress
Evaluation: In Progress
Report: In Progress
Accomplishments from Previous Week
Created final test rig (able to test both flow meters at same time)
Gathered 1-hour Calibration of Flow Meter Data
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Calibrate Both Flow Meters (Scott and Zeeshan)
Gather Data to Support Determined Optimal Distance Between Transducers (Becky and Jun)
Determine Optimal Angle Between Transducers (Becky and Jun)
Individual Concepts for Mounting Device Finished (Each member individually)
Agree on Design for Mounting Device (Team and CMA)
Continue Progress on Report (Team)
Poster Development (Team)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Obtain evidence to support optimal distance between transducers - performing series of tests comparing 1) flows across various bounces at optimal distances, and 2) flows at various distances at optimal number of bounces
Come up with concepts for mounting transducers onto pipe in seepage meter - Individual team members came up with own design and will collaborate on Thursday to configure best option
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
For obtaining flow of water, use a digital filter versus averaging - Began literature search on filtering. Will take research and present to sponsors at the weekly meeting.
Determine relationships between pipe parameters and transducer distance - Obtained appropriate contact information from sponsor to begin search (Flexim Headquarters)
Risks and Areas of Concern
Flow meters are too large to retrofit into current housing assemble
Resources or Information Required but not Available
Flexim data explaining the relationship between the parameters and bounce number
Schedule
Week 8:
Mon: Calibration of Flow Meter (1-hour tests)
Tu-W: Optimal Distance Transducers (gather data)
Thurs: Optimal Angle Between Transducers
Thurs: Collaborate on Mounting Device
Week 9:
Sun-Th: Test Various Pipes
Sun-Th: Retrofit Design onto Current Housing
Sun-Th: Trident Probe Mounting Design
Week 10:
Sat-M: Compile Data into Excel Workbooks
Budget (list amount spent and amount remaining)
Spent: $55
Remaining: $945
Progress on Report and Webpage
Report Grammar Fixed
Continuing filling in remaining sections for 2nd draft
Fabrication Analysis (Scott)
Cost Analysis (Scott)
Prototype and Final Design (Becky)
Users/Operation (Jun)
Performance and conclusions (Zeeshan)
Webpage pictures uploaded