Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Buoy frame assembly complete
Ballast Mounted
Accomplishments from Previous Week
Acquired Batteries
Acquired Aluminum tubing
Acquired Speed rail Fixtures
Constructed Buoy Frame
Attached Ballast to Buoy Frame
Fuel Cells Shipped
Machine perfect horizon mounting plate
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Mount Batteries in water Proof Container (All)
Get EFOY fuel cell (All)
Mount Fuel cell (All)
Wire Buoy-Cam (All)
Work on info logging for the solar panels when they arrive (All)
Order video transmission equipment (Nick)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Risks and Areas of Concern
Sponsor still needs to fill out an "Evalation purchase order" for the Solar Panels
Will the solar panels arrive one time?
Lead time on video equipment
It's the end of week 7
Charging a 24v battery system with 12v power source
Resources or Information Required but not Available
Schedule
Work on report
Order video transmission system
Continue buoy assembly
Update Gantt chart.
Budget (list amount spent and amount remaining)
Progress on Report and Webpage
The Webpage is coming together nicely