Guidelines for Report
Weekly Progress Reports should be printed out before meetings with the sponsor and instructor.
All team members should be able to explain all items on the progress report.
To start a new progress report, create a new webpage and use the Progress Report Template.
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Adjust CNC program for mitchel plate
Design smaller gimball system.
We currently have a buoy that can support up to 1,000 lbs
Completed CADing the buoy and miniature Perfect Horizon prototype
Accomplishments from Previous Week
Communicated with our Sponsor about the status of the miniature Perfect Horizon
Our Sponsor has another person designing and prototyping a miniature Perfect Horizon
Complete Ind. Component Analysis of Buoy-Cam system
Updated team website
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Design the Solar Panel frames to mount the solar panels (All)
Order components (All)
Cut out mitchelle plates (Ogi)
Meet with Sponsor to discuss about ordering components (All)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments
Will be meeting with Sponsor later on in the week
Sponsor has been unreachable
Instructor Comments from Last Meeting and Actions Taken to Address these Comments
Add more to weekly progress reports.
Updated the webpage
Upload Individual Component report files
Scheduling a meeting with our Sponsor
Risks and Areas of Concern
We are still in the Design phase and incomplete Buoy-Cam design will result in great delay in finishing the project
Underwater Battery Enclosure
Lead time for motors
Product may take significant time to arrive
The goal is to order parts by the end of Week 2
Smaller electronic parts can be purchased at department stores
Resources or Information Required but not Available
Parts-wise we still require:
Solar Panels
Wind Turbine
electrical wires
batteries
Information:
Talk to Tom and Isaiah about the best material to used to fabricate the solar panel mounts
Schedule
To order specific parts by end of Week 2
Complete Buoy-Cam design by end of Week 3
We will be fabricating solar panel mounts, and wind turbine mounts
Want to finish production of an initial Prototype by end of Week 5
Budget (list amount spent and amount remaining)
Current spending: $0.00
Progress on Report and Webpage
Complete Individual Reports
Updating Webpage to current deadline