Post date: Mar 08, 2018 8:39:30 PM
As of last week, the traffic pattern along Water Street was adjusted from the west to the east side of the road. We are still scheduled to be out of Water Street and return to a normal traffic pattern at the end of March.
We are nearing the Latham and Meacham Street intersection with the culvert installation. It looks like we are tracking to close Latham Street from the intersection of Meacham Street up to the Facilities Parking Lot sometime during the week of March 26. Latham will remain closed for 4-6 weeks.
We are exploring ways to lessen the closure period, which may involve making Latham one lane during the day, two lanes at night and during weekends - but this is still in planning. If this becomes a viable option, we will review with everyone prior to implementation.
Any questions - let me know.
Thanks
…
Jason Moran
Senior Project Manager
Williams College