Sprint Burndown

(Placeholder only: author page)

Context: the ScrumTeam has reported its status through the DailyScrum

Problem:What is the best way to provide the overall status for the team?

Forces: activity vs backlog

Solution:Provide a SprintBurndown as overall status of the ScrumTeam in the Sprint. A SprintBurndown is a graph of remaining estimated time to completion for the whole team vs time. This graph provides the status by saying "this is the time we need as a whole to complete what we agreed upon in this Sprint". Other units other than time can be used such as story points, chocolate points, or whatever else the ScrumTeam has agreed upon.

Resulting Context:The ScrumTeam knows where it stands in regards to accomplishing the Sprint