Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Waited on final parts to arrive
Sponsors 3D printed OX plates as part of contingency plan
Started 3D printing cantilever arm and storage
There were some issues with heat distribution so the sponsors were asked to work on it further
Accomplishments from Previous Week
Worked on the website and report
Submitted for sponsor approval and comments
Added all fasteners to the assembly on SolidWorks
Made progress on engineering drawings and submitted for machinist critique
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Finish mechanically building translation system (Kieu, Angela, Alanna)
Finish engineering drawings (All)
Finish Arduino libraries and begin automation code (Manuel)
Ensure all stepper motor drivers work properly (Manuel)
Select and order supplies for wiring of translational system (Manuel, Kieu)
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Professor Fenning made comments on our report and website
Liked front page video of gripper mechanism
Requested simulations for further visualization
Asked for isometric views of entire assembly to include in his presentation
Asked for further design recommendations for further iterations
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
The team expressed a possible need to expand the budget
Professor suggested prioritizing project success over costs
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
No comments were provided by other students in the class
Risks and Areas of Concern
No apparent risks exist at this time
With tight schedule, we hope to finish the prototype in time
Resources or Information Required but not Available
We lack access to a lasercutter or heavy machinery
Schedule
The updated GANTT chart is included in its tab
If all parts arrive this week, we hope to finish building the translation system
Budget (list amount spent and amount remaining)
Progress on Report and Webpage
Progress on the report and website is being made as the project continues