Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Reviving the previous design
try our best to get the prototype done by the end of this week.
Accomplishments from Previous Week
Photointerruptor prototype
Calibrating/testing system. Communication of the system.
How the previous system works with the ComPort.
Time with Steve Roberts about the RaspberryPi. No not going to invest time in this, and focus more on mechanical part.
Consisting on using the PCB board from last year.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Photointerruptor housing finalized
Test with mouse (confirm with sponsor meeting)
Look into clean/flushing the system, valve connector
Talking to Ian about that
Diagnose pressure sensor and recalibration
Determine wired or wireless (ask sponsor on Thursday meeting 1/23/20)
Sara and benson sync stuff
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Maybe need hard plastic for the photo interrupter housing
glue and need more support of the interrupter housing (better to not using glue) OR maybe we can have a clipping system that can have one part from outside and one part inside
select the solution on the GUI, and save the data in to CSV file with a input file name (auto dates, input mouse ID and etc)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Create User Manual
Next time: very brief, what led you to make decisions, accomplishments
Decision making process
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
NA
Risks and Areas of Concern
cage washing with industrial machine
need reinforcement on the edge of the hole
TTL on 5 volts while the current system using 3.3V
Resources or Information Required but not Available
the material of plastic box
Schedule
prototype by this week
Buy and test the quick release connecter
Buy and test the new tube material
Decision on wireless or cable
Budget (list amount spent and amount remaining)
Spent: 116.65
Remaining 1883.35
Progress on Report and Webpage
updated