Overview of Status of Analysis, Design, Fabrication, Tests, etc.
Sponsor testing
Mass production
Accomplishments from Previous Week
Assemble the whole system
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Build electronics
Assemble full system
Mass production
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Maybe the LED lights could be an indication that will in influence mice reactions.
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Final Report - GUI
structure, input, output
show screenshots
people should understand how to use the GUI
how to use the interface
pitfalls to mess-up; potential error for user
include code in appendix
GUI vs Data Acquisition - different sections in report
Sampling Rate
Serial port updating
Maybe meet w/ Professor with 1 complete system. By this Thursday?
Poster for poster session send to Darren 3 days before. Wear business casual.
Notes: be concise, don't go into too much detail, only what is necessary.
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
NA
Risks and Areas of Concern
The precision of glass tubes is not good. Need calibration whenever change the tube
Resources or Information Required but not Available
None
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Spent 919.14, Remaining 1080.86
Progress on Report and Webpage
modified some details online
added more pictures and informations