156B Week 9
Overview of Status of Analysis, Design, Fabrication, Tests, etc.
So far 2 segments have been assembled
Multiple segment communication is not yet achieved
Having trouble with some motors not responding
Accomplishments from Previous Week
Individual IMU's were tested and all have working pitch, yaw, and roll readings.
Goals for Next Week (list names after each item). Use specific and measurable objectives.
Solder PCB stack
Find what issue is causing motors to not run
Determine how serial communication is achieved with multiple segments
Sponsor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Instructor Comments from Last Meeting and Actions Taken to Address these Comments (indicate date of comments and if via email or in person)
Comments from Other Students in the Class (indicate date of comments and if via email or in person)
Risks and Areas of Concern
Resources or Information Required but not Available
Schedule
Describe upcoming milestone
Update Gantt chart.
Budget (list amount spent and amount remaining)
Progress on Report and Webpage